How To Install D Type Hydraupulper
Before the installation, the base of the D Type Hydraupulper must be poured in accordance with the general layout and basic drawing, the following points should be taken into account:
The free space should be large enough to allow the rotor device to be moved or removed by the vehicle, the crane beam or the hoist. Pulp feeding pump of D Type hydraupulper should be as close as possible to Pulper and under it. Pulp outlet pipe should be as short and simple as possible. The belt conveyor should be placed at the straight edge of the body of the Pulper to make the pulp fall on the side of the rotor and rotate counter-clockwise with the pulp.
1. According to the requirements of the basic drawing, the center line should be correctly determined, the corresponding position and size should be corrected, and the reinforced concrete grouting equipment foundation should be used.
2. Open the box and check whether the parts are complete.
3. After a certain maintenance period (usually 15 days) and corrections, the equipment can be installed.
leizhan company has more than thirty years experience in making pulping and paper machine, we are not only supply the D Type continuous pulping system, but also help you install it, our engineer can teach you or go to your paper mill to help you install D Type Hydraupulper. If you need Hydraupulper or other papermaking machine, welcome to contact us.